|
Aside the present Piacenza power plant,
today we can still find the old
"Emilia", the
former power plant designed by architect Piero Portaluppi in years 1925-26 and considered a wonderful monument to man work.
The works for its construction were carried out by many skilled Italian
companies employing more than 1,000 workers.
Two turbogenerators units
"Westinghouse" of 70
MW each were operated
in the equipment room, and the total efficiency of the plant was above 35%, in
line with the best technologies available at that time in thermal power plants
installed in Europe.
The tecnology adopted in the power plant
was the "single
unit" one, that is
(based on the steam supply of each turbogenerator by one single boiler) without
connections between the two units.
The steam production capability of each boiler of Emilia
Power Plant was more
than 210 t/h at 103 atm pressure.
Between 1965 and 1967, two conventional
330 MW units were erected in a building (named the “Levante Power Plant”), in
front of the old Emilia Power Plant.
TECHNICAL
OUTLOOK
As provided for in D.M. 9/2001, Edipower
implemented the revamping of the Levante Power Plant into a modern gas turbine combined
cycle, consisting of two
gas turbines and one steam turbine having total capacity of approximately 800
MW.
With the post-combustion system installed
in the recovery boilers, it is possible to increase the steam production and
obtain an increase
of 50 MW on the power output of the steam turbine.
The preliminary works for the site began
on 30 December 2002 and the combine cycle commissioning occurred in December 2005.
The new plant is equipped with:
- 2
gas turbines
- 2
heat Recovery Steam Generators , equipped with 90 m height stacks for gas
exhaust
- 1
steam turbine using the steam produced by the two heat recovery steam
generators
- 1
steam condenser
- 3
generators
- 3
main transformers
The condenser cooling water is taken
from the Po River and returned to the same using the existing intake and
discharge works.
The total efficiency of the plant
is equal to 56%.
THE
AGREEMENT WITH THE MUNICIPALITY
Based on the agreement signed with Piacenza Municipality in February 2005, the Piacenza
power plant – from 2006 to 2010 – shall supply heat for the town district heating system, up to 20 MWt and, after 2010,
up to 160 MWt.
With the dismantling of civil boilers,
the district heating system shall allow a highly significant pollutant reduction in the air.
The agreement signed between Edipower
and the Municipality of Piacenza includes also a contribution for the Emilia Power Plant Integrated
Project.
The Integrated Project envisages the
partial recovery of Emilia Power Plant to house the Leap Consortium – a
laboratory for the efficiency and environmental compatibility of power
technologies – and a area for a museum dedicated to the town.
TECHNICAL
DESCRIPTION
GAS TURBINES
The two gas turbines (GT) installed in
the combined cycle have a power output of approx. 270 MWe each.
Each one includes the axial air
compressor that supplies the necessary air for the combustion and cooling of
the hot parts of the equipment.
The burners are of the low NOx type to limit emissions within the limits
requested by the regulations in force.
The thermal power supplied by combustion
is transformed into mechanical power in the gas turbine and then into electric
power through the coupled generator.
Flue gas coming out from the gas
turbines is sent to the heat recovery steam generators, where it exchanges heat
for steam production and, then, is discharged at the stack.
HEAR RECOVERY
STEAM GENERATORS
Heat Recovery Steam Generators (HRSG) are
surface heat exchangers that, using the thermal power of flue gas of the GTs,
produce the steam necessary to operate the Steam Turbine.
STEAM TURBINES
The main technical data are:
- Type:
4 cylinder impulse-reaction
- Capacityr:
340 MW
- Steam
Pressure: SH 171 Ata
- Steam
Pressure: RH 45 Ata
- Steam
Temperature: SH 538°C
- Steam
Temperature: RH 538°C
- Pressure
at discharge: 0.050 Ata
GENERATORS
The two generators coupled to the gas
turbines are of the three-phase type, cooled in closed cycle hydrogen atmosphere.
The third generator (the one coupled to the steam turbine)
is of the three-phase type with mixed cooling (closed cycle hydrogen atmosphere and closed
cycle deionised water cooling for stator windings).
MAIN TRANSFORMERS
Each generator is connected to its main transformer
that increases voltage up to 380 KV to
enable electric power to be inlet in the transmission grid.
CONDENSERS
The condenser is of the surface type, with one-way horizontal pipes, crossed by the water of the Po River.
The steam discharged by low pressure stages of the turbine, passing in the
pipes, condenses and transforms into water, which is collected in the hot well
and, taken by extraction pumps, is newly sent to the HRSGs, after
physical-chemical filtration treatment.
FUELS
The combined cycle is
natural gas fired only. Gas is supplied through a gas pipeline connected to the national gas
grid.
The Piacenza Power Plant is equipped
with:
- "low NOx" combustion systems to reduce the
emissions of nitrogen oxides (NOx).
The emissions to the atmosphere of
nitrogen oxides (NOx), sulphur dioxide (SO2), particulate and carbon
monoxide (CO) are monitored and continuously recorded through an Emission Monitoring System (SME); measured values are transmitted every
week to the relevant control authority (ARPA).
The Air Quality Monitoring Network (RRQA) for the measurement of some pollutants in
the ground is owned and managed by the Province; the Piacenza Power Plant
contributed to the costs for the implementation and management of the network
itself.
The waste waters (acid/alkaline, oily,
biological) are treated in a purposely designed plant (ITAR, Waste Water Treatment Plant) and continuously tested before the
discharge.
All activities that interact or may
interact with the environment are managed in accordance with the ruling
environmental laws and the available state–of-the-art techniques.
The Environmental Management System
implemented in the power plant was certified in May 2003 according to the UNI
EN ISO Std. 14001.
To foster the ongoing improvement of the
environmental performances and the information to the public, the management of
the Piacenza Power Plant has voluntarily adopted the EU Ecomanagement and Audit
Scheme (EMAS) and obtained the registration in November 12, 2003 with the
number I-000167.

|