Under the management of Ing. Luigi Selmo, the design and erection of the Chivasso
Power Plant started in June 1950, taking in consideration the
possibility of future extension with the installation of other units.
The first unit was commissioned in 1953 and in the first years of operation, natural gas,
coal, and fuel oil were used as boiler fuels.
The second unit was commissioned in 1956 whereas the third and the fourth units, fuel oil fired only, came into operation in 1959. In 1962, also
the 30 MW gas
turbine section,
located in a dedicated building, came into operation.
We have to wait until 1966 to see the fifth unit (fuel oil fired) in operation, which represented,
with its 250 MW, the largest section of the Chivasso Power
Plant.
In 1975, in order to use also natural gas as fuel, units 4 and 5 were transformed, thus following the diversification strategy in
the procurement of fuel resources.
The maximum production period is recorded right between 1967 and 1980. Afterwards, with the commissioning of
more advanced power plants having higher efficiency, the Chivasso Power Plant was
used only in peak periods until 1992, when the unit 3 (gas turbine) was officially shut down, and, on the same date, also the
units 1 and 2 were shutdown.
In 2002, to allow the construction of the modern combined
cycle plant, currently in operation, also units 4 and 5 were shutdown.
TECHNICAL
OUTLOOK
The old power plant, located between the
left side of Po River and the entrance of the Cavour Channel, in the area of
Chivasso municipality, has been transformed into a modern gas turbine plant
with combined cycle gas turbine units.
The new plant, commissioned at the end
of 2004, has a total capacity of approx. 1,170 MW (performance test).
The new power plant is located in an area
of approx. 400.000 m2 and consists of two gas turbine combined cycle production units (defined Modules):
- one module (CH1) consisting of two
production sections with gas turbine and of a production section with steam
turbine, for a total capacity of 790 MW.
- one module (CH2) consisting of one
production section with gas turbine and one production section with steam
turbine, for a total capacity of 381 MW.
The plant is fed with natural gas only.
The power plant is equipped with:
- 3
gas turbines
- 3
heat recovery steam generators
- 2 steam turbines
- 2
steam condensers
- 5
generators
- 5
main transformers
- 3
stacks, 90 m high
TECHNICAL
DESCRIPTION
GAS TURBINES
The gas turbines installed in the combined
cycle have a single shaft, and are able to reach a power output of
approximately 250 MW.
The multistage axial compressor is equipped with inlet guide vanes (IGV).
A withdrawal of compressed air is used
for the cooling of the turbine and to avoid the pumping phenomenon during the
start up.
Air exhausted by the axial compressor is
sent to the combustion chamber.
The burner is of the dry low NOx type (Dry Low NOx, reverse flow DLN-2) with 18 combustors arranged in a circular array on the discharge section
of the compressor.
The heat generated by the combustion is
transformed into mechanical power in the gas turbine and then in electricity
through the coupled generator. The flue gas coming out from the gas turbines is
sent to the heat recovery steam generators (HRSG), where it releases heat for
steam production, and then it is discharged from the stack.
STEAM TURBINES
The steam turbines of Module 1 and of
Module 2 are of the impulse/reaction type and consist of three cylinders (high pressure, intermediate pressure
and low pressure) installed on the same axis.
GENERATORS
Generators are of the three-phase type, with cooling in closed cycle hydrogen atmosphere. The generator of the steam turbine of Module
2 is fit with an additional demineralised water cooling system of the stator
winding (fixed winding).
MAIN TRANSFORMERS
The electricity produced by the power
plant is inlet in the transmission grid, partly at 230 kV voltage and partly at
400 kV voltage through the 5 main transformers.
HEAT RECOVERY
STEAM GENERATORS
The Module 1 is equipped with two heat
recovery steam generators (HRSG) whereas Module 2 with one HRSG. These HRGs produce
steam using the flue gas discharged by the relevant gas turbines.
CONDENSERS
Condensers are of the surface type with one-way horizontal pipes (Module 1) and
two-way pipes (Module 2) and two independent half-casings on the river water
side. The condensate, collected in the hot well of the condenser, is pumped out
by extraction pumps to be sent, after filtration and treatment, to the drums
of the HRSGs.
The condenser cooling water is taken
from the Po River, upstream the intake of the Cavour Channel and can be
discharged in the same channel or through a secondary discharge channel directly
to the Po River.
FUELS
The fuel used in the Chivasso Power Plant
is natural gas
only. A gas pipeline connects directly the
plant to the national gas grid and the gas pressure is reduced, through a pressure
reduction station, to the correct value for the operation of the gas turbines.
To minimize the emissions to the air the
power plant is equipped with combustion systems enabling the dry (Dry Low NOx)
reduction of nitrogen oxides (NOx).
The power plant is equipped with an Air Quality Monitoring Network
(RRQA), consisting of
two measurement workstations (located in the municipalities of Chivasso and
Castagneto Po), which measure the discharge of pollutants on the ground.
Recently, new instruments have been installed on both stations. The data are
periodically transmitted to ARPA Piemonte and Chivasso municipality.
The emissions to air of nitrogen oxides (NOx)
and carbon monoxide (CO) are continuously monitored and recorded through an Emission Monitoring System (SME); the measured data is transmitted, in real
time, to the Control Authority (ARPA).
The waste waters (acid/alkaline, oily,
biological) are treated in a purposely designed plant (ITAR) and continuously tested before the discharge.
The management of the Thermal Power
Plant has implemented an Environmental Management System that was certified according to the UNI EN
ISO Standard 14001 in
December 2002..
To foster the ongoing improvement of the
environmental performances and the information to the public the management of
the power plant has voluntarily adopted the EU Ecomanagement and Audit Scheme
(EMAS) and obtained the registration in December 19, 2003 with the number I-000176.
|